Before signing a turnkey renovation, always ask for two documents alongside the quotation: the specification, which describes how each piece of work will be done and with which materials, and the schedule, that is, the site programme by stages. The quotation says how much; the specification says how; the schedule says when.
The specification
The specification is the technical description of the work: how demolition and disposal are done, what the new walls are built with, which services are installed and with which components, which stone, in what thickness and finish, how it is laid and polished in place, which windows and doors. At Michelessi the specification grows out of the 3D design: every room is already drawn with its materials, and the document puts them in writing. A "renovation specification example" found online is generic: yours must name your own home, room by room.
The schedule
The schedule is the site programme by stages, in the same order as the items in the quotation: demolition, building work, services, screeds, stone, windows and walls, furnishing and styling, handover. We write it only after the survey and the design, because timing is set by the square metres, the condition of the house, the building permits and the materials chosen: a slab of onyx does not arrive in the same time as a Carrara. Then we review it together at every change of stage. Be wary of anyone who promises a date before seeing the house and checking the permits: the municipality's timing does not depend on the renovator.
What happens at handover
Handover closes the circle: final cleaning, testing of the services, delivery of the declarations of conformity and of the services drawings, and the house ready to live in, with the paintings hung, the curtains up, the towels in their niches and the table laid.